Prioritization frameworks cheat sheet

No framework decides for you. Each makes a different assumption visible so the argument is about the right thing.

Scoring models

RICE
Reach × Impact × Confidence ÷ Effort. Good for comparing many small bets.
ICE
Impact × Confidence × Ease. Faster, rougher than RICE.
Cost of delay
Value lost per week of waiting.
CD3
Cost of delay ÷ Duration. Do the highest first.
Value vs effort
2×2: quick wins first, money pits never.

Categorization

MoSCoW
Must, Should, Could, Won't (this time). Good for fixed-scope releases.
Kano
Basic needs, performance features, delighters.
Eisenhower
Urgent × Important: do, schedule, delegate, drop.
Now / Next / Later
Roadmap without false dates.

Blind spots

False precision
Scores are guesses; compare in bands, not decimals.
Effort bias
RICE favors small work; strategic bets need a separate lane.
Keep-the-lights-on
Reserve capacity for reliability before scoring features.
Dependencies
A low-scoring item may unblock high-scoring ones.

Try it — Cost of delay

CD3 of A

5,000

CD3 of B

7,500

Delay cost, A first

$470,000

Delay cost, B first

$430,000

Do B first: the order with the higher CD3 saves $40,000 in value lost while waiting. One team, one project at a time; each project loses its weekly value for every week until it ships.

Test yourself

Questions from the lessons behind this sheet, explained when you check them.

Question 1

Q1.A project's cost of delay is $30,000 a week and it takes six weeks. What is its CD3?

Question 2

Q2.A fake-door test — a button for a feature that does not exist yet — mainly tests which risk?

Question 3

Q3.Rumelt's kernel of good strategy consists of…