Every yes is a no to something else. Make the trade explicit.

Every yes is a no to something else. The opportunity cost of a project is the value of the best alternative you did not do. Prioritization frameworks exist to make that trade explicit, instead of leaving it to whoever argues loudest.

RICE scores an initiative as Reach × Impact × Confidence ÷ Effort. Reach is how many users or events per period, impact is a scaled estimate per user, confidence discounts guesswork, and effort is person-months. The score is value per unit of effort — good for comparing options, not for false precision.

Cost of delay asks what each week without this costs you. Dividing cost of delay by duration (CD3) gives a sequencing rule: do short, urgent, valuable things first. A small job worth $10,000 a week can beat a large job worth $30,000 a week if it ships five times faster.

Picture it

Two projects compete for one team. A is worth $40,000 a week once live and takes eight weeks. B is worth $15,000 a week and takes two. A sounds bigger, but its CD3 is 5,000 against B's 7,500. Doing B first costs $430,000 in total delay; doing A first costs $470,000. Sequencing alone is worth $40,000.

Key formulas & frameworks

Opportunity cost
Value of the best alternative you gave up
RICE score
(Reach × Impact × Confidence) ÷ Effort
CD3
Cost of delay ÷ Duration — do the highest first

Try it — Cost of delay

CD3 of A

5,000

CD3 of B

7,500

Delay cost, A first

$470,000

Delay cost, B first

$430,000

Do B first: the order with the higher CD3 saves $40,000 in value lost while waiting. One team, one project at a time; each project loses its weekly value for every week until it ships.

Practice

Score: 0 / 5

Question 1

Q1.An initiative has a reach of 2,000, impact of 2, confidence of 50% and effort of 4 person-months. What is its RICE score?

Question 2

Q2.A project's cost of delay is $30,000 a week and it takes six weeks. What is its CD3?

Question 3

Q3.X is worth $20,000 a week and takes ten weeks. Y is worth $9,000 a week and takes three weeks. By CD3, which goes first?

Question 4

Q4.The opportunity cost of a project is the money spent on it.

Question 5

Q5.What is confidence for in a RICE score?