Business Fundamentals

Lesson 5 · Finance

Budgets, headcount & capex vs opex

People are the budget. Learn what a hire really costs and how spend hits the books.

In most engineering organizations, people are by far the largest cost. The fully loaded cost of an employee — salary plus benefits, payroll taxes, equipment and overhead — commonly runs 1.25 to 1.4 times base salary. A budget is the plan for that spend, and variance is the gap between plan and actual.

Capital expenditure (capex) buys assets that last for years; its cost is spread over the asset's useful life as depreciation. Operating expenditure (opex) is expensed as it is incurred. Moving from owned servers to cloud shifted infrastructure from capex to opex. Some software development can be capitalized too, which changes how its cost appears on the P&L.

Burn is net cash out per month, and runway is cash divided by burn. When you ask for headcount you are asking for a recurring commitment, so present it as an annual fully loaded cost set against the outcome it buys.

Picture it

Dan asks for “just two more engineers” at a $160,000 base. At a 1.3× load that is $416,000 a year, every year. His director asks what it buys. Dan reframes: the two hires unblock an integration worth $1.2M in annual contract value. Now it is an investment rather than a cost.

Key formulas & frameworks

Fully loaded cost
Base salary × Load factor (≈ 1.25–1.4)
Budget variance
Actual − Budget
Straight-line depreciation
Asset cost ÷ Useful life
Runway (months)
Cash ÷ Monthly net burn

Try it — Team cost

Annual team cost

$1,248,000

Per two-week sprint

$48,000

Per engineer-hour

$116

One-hour all-team meeting

$693

Fully loaded cost is base salary times the load factor; the hourly figure assumes about 1,800 working hours a year. Use the sprint number when someone asks for “a quick two-week project”.

Practice

Score: 0 / 5

Question 1

Q1.Five engineers have an average base salary of $150,000 and the load factor is 1.3. What is the team's annual fully loaded cost, in dollars?

Question 2

Q2.A company buys $600,000 of servers with a four-year useful life, depreciated straight-line. How much expense hits this year's P&L?

Question 3

Q3.A startup has $3M in cash and a net burn of $250,000 a month. How many months of runway does it have?

Question 4

Q4.A monthly cloud bill is typically operating expenditure rather than capital expenditure.

Question 5

Q5.The budget was $500,000 and actual spend was $560,000. The variance is…